Project Area
Our working area for this project


South Runway
In South Runway, we are working on paving, marking, restructuring, and instal new AFL System.


North Taxiway
In North Taxiway, we are working on reconstruction and cable instalation for AFL
Progress Percentage
Until now we are still working on this project
83.79%
78
Weeks
Progress